Free email alerts →
Capacity (MW)
Status: active
Show projects that are

Always included while Built, Withdrawn, Status unknown or Postponed is ticked.

Status not current MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0)

Status not current

The status is the one the file states on that date, not the register’s current one.

1,585 projects

Active only

What this view shows

Showing 1,585 active projects (announced to under construction). Hidden: 33 withdrawn or cancelled, 40 built, 1,025 postponed or unknown-state. Use Status in the filters to show them.

68 projects no register lists any more are hidden. Show them

Save this search as an alert Free, daily or weekly.

Projects matching the current filters, sorted by capacity, largest first by default.
Status Name. Sort by name, A to Z Technology Capacity (MW), sorted descending. Sort by capacity, smallest first Location Company Proposed online. Sort by proposed online date, latest first Source
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Project Matador Gas Plant (PMG) Gas, combined cycle 11,679.3 MW Carson, TXFermi America Online 1 Dec 2027 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Project Matador Nuclear Nuclear 4,468 MW Carson, TXFermi Nuclear Online 1 Dec 2031 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Homer City Generating Station Gas, combined cycle 4,396 MW Indiana, PAHomer City Generation, L.P. Online 1 Nov 2029 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Chokecherry and Sierra Madre Wind Wind 3,550.5 MW Carbon, WYPower Company of Wyoming LLC Online 1 Dec 2032 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Coastal Virginia Offshore Wind (CVOW) Commercial Project Offshore wind 2,640 MW VADominion Energy Inc. Online 1 Jan 2027 us.permits_dashboard
Filed (source status: (L) Regulatory approvals pending. Not under construction) Pepper Hammock Solar and Storage Solar + storage 2,500 MW Wayne, GABrightNight Power Online 1 Sep 2029 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Sunstone Solar Solar + storage 2,400 MW Morrow, ORSunstone Solar, LLC Online 1 Dec 2027 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Pointe Coupee Power Station Gas, combined cycle 2,340.9 MW Pointe Coupee, LAEntergy Louisiana LLC Online 1 Oct 2031 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Deschutes Solar and BESS Solar + storage 2,000 MW Wasco, ORDECH bn, LLC Online 1 Nov 2029 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Kingston Gas, combined cycle 1,830.6 MW Roane, TNTennessee Valley Authority Online 1 Dec 2027 EIA-860M
Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) Richland Parish Power Station 1&2 Gas, other 1,640 MW Richland, LAEntergy Louisiana LLC Online 4 Aug 2028 EIA-860M
Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) Franklin Farms 1&2 Gas, other 1,640 MW Richland, LAEntergy Louisiana LLC Online 4 Aug 2028 us.lbnl.queued_up
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Cumberland (TN) Gas, combined cycle 1,555.6 MW Stewart, TNTennessee Valley Authority Online 1 Dec 2034 EIA-860M
Studied (source status: Active) Aegle Power Gas, combined cycle 1,536.4 MW Cameron, TXCoronado Power Ventures LLC Online 30 Jul 2027 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Bison Generation Station Gas, combined cycle 1,518 MW Williams, NDBasin Electric Power Coop Online 1 Feb 2029 EIA-860M
Under construction (source status: (V) Under construction, more than 50 percent complete) Yates Gas, combustion turbine 1,448.4 MW Coweta, GAGeorgia Power Co Online 1 Feb 2027 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Libra Solar Solar + storage 1,400 MW Lyon, NVLibra Solar LLC Online 1 Dec 2027 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Sanborn Hybrid 3 Solar + storage 1,400 MW Kern, CATerra-Gen Operating Co-Hybrid Online 1 Dec 2026 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Comanche (OK) Gas, combined cycle 1,372.8 MW Comanche, OKPublic Service Co of Oklahoma Online 1 Sep 2029 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) CPV Basin Ranch Energy Center Gas, combined cycle 1,350 MW Ward, TXCPV Basin Ranch Online 1 Feb 2029 EIA-860M
Under construction (source status: (TS) Construction complete, but not yet in commercial operation) Orange County Advanced Power Station Gas, combined cycle 1,306 MW Orange, TXEntergy Texas Inc. Online 1 Oct 2026 EIA-860M
Studied (source status: Active) Sandow Lakes Energy Station Gas, combustion turbine 1,291.6 MW Lee, TXSL Energy Power Plant I, LLC Online 1 Apr 2028 ERCOT
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Lincoln Land Energy Center Gas, combined cycle 1,276.8 MW Sangamon, ILLincoln Land Energy Center LLC Online 1 Jun 2030 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Saddleback Generation Station Gas, combined cycle 1,250 MW Maricopa, AZCopia Power Online 1 Dec 2030 EIA-860M
Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) Red Oak Ridge Energy Center LLC Gas, other 1,211.2 MW Kenosha, WIInvenergy Services LLC Online 1 Dec 2027 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Clear Fork Creek Solar and BESS SLF Solar + storage 1,202 MW Wilson, TXClear Fork Online 1 Mar 2027 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Hop Hill Solar Generation and BESS Solar 1,200 MW Benton, WAHOHI bn, LLC Online 1 Sep 2031 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Steward Creek Solar Phase 1 Solar 1,200 MW Lee, ILTerraForm Power Operating, LLC Online 1 Dec 2029 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Vista Sands Solar Solar 1,182 MW Portage, WIVista Sands Solar LLC Online 1 Dec 2028 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) South Oak Creek Gas, combustion turbine 1,181.5 MW Milwaukee, WIWisconsin Electric Power Co Online 1 Feb 2028 EIA-860M
Contracted Darden I Solar Solar + storage 1,150 MW Fresno, CAIntersect USA, LLC Online 19 Jul 2027 CAISO
Filed (source status: (L) Regulatory approvals pending. Not under construction) NTEC Gas Plant Gas, combustion turbine 1,089 MW San Juan, NMNavajo Transitional Energy Company Online 1 Jun 2028 EIA-860M
Contracted (source status: Completed) Sunscape Renewable Energy Solar + storage 1,022.8 MW Nueces, TXVesper Energy Development LLC Online 31 Oct 2028 ERCOT
Studied (source status: Active) Hecate Energy Harley Hand Solar LLC Solar + storage 1,008.9 MW Nolan, TXHecate Energy Harley Hand Solar LLC Online 7 Apr 2029 ERCOT
Filed (source status: (L) Regulatory approvals pending. Not under construction) Chesterfield Gas, combustion turbine 1,000 MW Chesterfield, VAVirginia Electric & Power Co Online 1 Jun 2029 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Haiwee Pumped Storage Project Pumped hydro storage 1,000 MW Inyo, CAPremium Energy Holdings Online 1 Jul 2028 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Intermountain Pumped Storage Project Pumped hydro storage 1,000 MW Millard, UTPremium Energy Holdings Online 1 Jul 2028 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Dutchman Solar generation and BESS Solar + storage 998 MW Converse, WYDUTC bn, LLC Online 1 Jun 2029 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Sycamore Riverside Energy, LLC Gas, combustion turbine 964 MW Sullivan, INInvenergy Services LLC Online 1 Mar 2029 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Arkansas Cypress Solar Station Solar + storage 950 MW Jefferson, AREntergy Arkansas LLC Online 1 Jan 2029 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Snowflake A Solar and BESS Solar + storage 950 MW Navajo, AZClenera DevCo LLC Online 1 Aug 2027 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Sunrise Wind Offshore wind 924 MW Suffolk, NYOrsted Wind Power North America LLC Online 1 Oct 2027 EIA-860M
Under construction (source status: (V) Under construction, more than 50 percent complete) Tehuacana Creek Solar Solar + storage 923.4 MW Navarro, TXParliament Energy Holdings LLC Online 1 May 2027 EIA-860M
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Naples Power Plant Gas, combustion turbine 900 MW Morris, TXArkansas Electric Coop Corp Online 1 Dec 2028 EIA-860M
Under construction (source status: (TS) Construction complete, but not yet in commercial operation) Horseshoe Lake Gas, combustion turbine 896 MW Oklahoma, OKOklahoma Gas & Electric Co Online 1 Oct 2026 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) Vast Sands Power Gas, combustion turbine 880 MW Ward, TXPermian Power I LLC Online 1 May 2027 ERCOT
Announced (source status: (P) Planned for installation, but regulatory approvals not initiated) Waterford 6 Gas, combined cycle 820 MW St Charles, LAEntergy Louisiana LLC Online 1 Jun 2030 EIA-860M
Filed (source status: (L) Regulatory approvals pending. Not under construction) Jefferson Power Station Gas, combined cycle 820 MW Jefferson, AREntergy Arkansas LLC Online 1 Nov 2029 EIA-860M
Under construction (source status: (U) Under construction, less than or equal to 50 percent complete) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) Vicksburg Advanced Power Station Gas, other 820 MW Warren, MSEntergy Mississippi LLC Online 1 Aug 2028 us.lbnl.queued_up
Studied (source status: active) (status as of the file: MISO queue as of 31 December 2025, compiled by Berkeley Lab and GridTracker (CC BY 4.0); not current) Legend Power Station Gas, other 820 MW Jefferson, TXEntergy Texas Inc. Online 25 Sep 2027 us.lbnl.queued_up

Sources EIA-860M · Permitting Dashboard · Berkeley Lab · ERCOT · CAISO

Sources

Attribution