Alta Wind VIII — Power plant · Wind · Nextera Energy ResourcesWindhub Solar B, LLC — Under construction · Solar · CA · 26.4 MW · 2.2 mi awayTehachapi Spindle — Withdrawn · Storage · CA · 20 MW · 2.6 mi awaySyracuse and Tours Renewable Energy — Permitted · Solar + storage · CA · 80 MW · 6.7 mi awaySanborn Hybrid 3 — Under construction · Solar + storage · CA · 1,400 MW · 7.2 mi awayAratina Solar Center 2 — Under construction · Solar + storage · CA · 200 MW · 8.7 mi awayWillow Rock Energy Storage Center — Contracted · Storage · CA · 500 MW · 9.0 mi awayTehachapi Wind Resource I — Postponed · Wind · CA · 0.6 MW · 9.1 mi awayBellefield 2 Solar & Energy Storage Farm — Under construction · Solar + storage · CA · 500 MW · 9.4 mi away4001 and 2510 ClearVista Solar and Wind — Withdrawn · Wind · CA · 24.5 MW · 10.5 mi awayCamino Solar Hybrid — Postponed · Storage · CA · 11 MW · 13.5 mi awayBellefield 3 Solar and Battery Storage — Contracted · Solar + storage · CA · 150 MW · 13.7 mi away
  • Wind & solar
  • Storage
  • In development
  • Under construction
  • Operating
  • 10 · 100 · 1,000 MW

Alta Wind VIII

Power plant · Wind

Key facts

Power plant · Windran 17% of 2025 Operating
Capacity
Capacity: sourceEIA-860M · Open licenseMW
Commissioned
2012
Net generation, 2025
219,153 MWh
Grid
230 kV to Southern California Edison Co (CISO)
Location
Kern County, California

Output

Net generation MWh by year, 2012 to 2025

Operations detail

Details

Who’s behind it

Interested in this project?

Set an alert Book a call Join the beta

Our team gets you what you need.

Beta: private project space · data room · readiness check

Technology
Wind source: “Onshore Wind Turbine”
Age
14 years since 2012
All 5 attributes from EIA-860M Preliminary Monthly Electric Generator Inventory
Attributes
AttributeValue
Grid
Nerc region
WECC
Report year
2025
Grid voltage kv
230
Transmission owner
Southern California Edison Co
Balancing authority code
CISO
Balancing authority name
California Independent System Operator
Fuel burned (MMBtu), 2025747,751
Capacity factor, 20250.167
Net generation (MWh), 2025219,153
Balancing authority codeCISO

Ownership

2 companies2
Companies with an ownership or operating interest in this asset.
CompanyRoleShareAs ofSource
Nextera Energy Resources Operator EIA-860M
Brookfield Renewable Energy Group Owner 100.0% Dec 31, 2025 EIA-860

Timeline

  • In service · EIA-860M

Around this plant

Nearby

within 15 mi
Projects within 15 mi, nearest first.
ProjectKindAwayMW
Windhub Solar B, LLC Under construction Solar 2.2 mi 26.4
Tehachapi Spindle Withdrawn Storage 2.6 mi 20
Syracuse and Tours Renewable Energy Permitted Solar + storage 6.7 mi 80
Sanborn Hybrid 3 Under construction Solar + storage 7.2 mi 1,400
Aratina Solar Center 2 Under construction Solar + storage 8.7 mi 200
Willow Rock Energy Storage Center Contracted Storage 9.0 mi 500
Tehachapi Wind Resource I Postponed Wind 9.1 mi 0.6
Bellefield 2 Solar & Energy Storage Farm Under construction Solar + storage 9.4 mi 500
4001 and 2510 ClearVista Solar and Wind Withdrawn Wind 10.5 mi 24.5
Camino Solar Hybrid Postponed Storage 13.5 mi 11
Bellefield 3 Solar and Battery Storage Contracted Solar + storage 13.7 mi 150

Sources EIA-860M · CAISO

Sources

  • EIA-860MOpen license · retrieved Nov 4, 2026
  • CAISOOpen license, with credit · retrieved Nov 13, 2026Source: California ISO

Attribution