- Combustion
- Clean firm
- Wind & solar
- Storage
- Under construction
- Operating
- Retired
- Other companies nearby
- 10 · 100 · 1,000 MW
Map
- Combustion
- Clean firm
- Wind & solar
- Storage
- Under construction
- Operating
- Retired
- Other companies nearby
32 assets · 5 projects
32 assets · 5 projects. Basemap: Protomaps, © OpenStreetMap contributors, ODbL.
Not on this map: 5 projects: placed by county or state, a license that withholds the site, or a stage the map draws no dot for (withdrawn, canceled, frozen or not stated). Each is in its tab below.
Duke Energy Progress - (NC)
Utility
Key facts
Utility · 16,077.1 MW- Capacity held
- 16,077.1MW
- Assets
- 32
- Projects
- 10
- States
- NC, SC
- Registered in
- United States
- Parent
- Duke EnergyOwnership claimOwnership link recorded from the companies' own published statements; no date stated by the source.
Gross output of plants with a stake
19 of 22 plantsOutputGross: each plant's whole output, whatever the stake. Equity share: each plant's output times the stake.Covers 19 of 22 plants with a stake: US plants with an EIA monthly series.100% of the output is from 19 plants recorded as wholly owned.18 plants: operator, wholly owned per EIA-860.Not included: 10 plants it operates without a recorded stake.Ownership as recorded today; each plant's output is its whole series. A plant's group is its technology; Unspecified fuel is EIA's "All Other", hydrogen, CHP with no fuel stated and plants with no technology on record.
- Gas
- Oil
- Nuclear
- Hydro
- Solar
- Storage
Yearly totals
| Year | Gas | Oil | Nuclear | Hydro | Solar | Storage | Total (MWh) |
|---|---|---|---|---|---|---|---|
| 2026 (part year) | 6,941,487 | — | 15,465,242 | — | 98,125 | -9,778 | 22,495,076 |
| 2025 | 9,891,747 | 98,018 | 23,541,250 | 406,427 | 256,115 | 397 | 34,193,954 |
| 2024 | 10,608,526 | 120,578 | 23,316,010 | 459,279 | 228,369 | 2,315 | 34,735,077 |
| 2023 | 10,355,482 | 116,109 | 24,267,354 | 486,741 | 259,898 | 1,666 | 35,487,250 |
| 2022 | 10,516,644 | 107,834 | 23,193,972 | 464,238 | 248,363 | 700 | 34,531,751 |
| 2021 | 9,927,800 | 105,332 | 23,455,593 | 572,747 | 253,261 | -205 | 34,314,528 |
| 2020 | 9,907,763 | 28,794 | 23,281,813 | 850,717 | 246,901 | -54 | 34,315,934 |
| 2019 | 11,409,218 | -956 | 22,327,350 | 673,862 | 252,502 | — | 34,661,976 |
| 2018 | 11,312,135 | 88,566 | 22,214,881 | 717,273 | 235,193 | — | 34,568,048 |
| 2017 | 12,093,191 | 83,849 | 23,578,728 | 396,774 | 255,986 | — | 36,408,528 |
| 2016 | 11,677,467 | 72,342 | 22,901,798 | 417,490 | 172,322 | — | 35,241,419 |
| 2015 | 11,175,801 | 99,454 | 22,560,759 | 482,917 | 5,745 | — | 34,324,676 |
| 2014 | 9,675,712 | 119,682 | 23,380,815 | 549,627 | — | — | 33,725,836 |
| 2013 | 7,054,143 | 149,044 | 21,344,131 | 815,479 | — | — | 29,362,797 |
| 2012 | 809,079 | 97,730 | 21,417,440 | 500,323 | — | — | 22,824,572 |
| 2011 | 155,464 | 97,240 | 22,677,187 | 504,272 | — | — | 23,434,163 |
| 2010 | 351,347 | 119,327 | 21,889,103 | 488,506 | — | — | 22,848,283 |
| 2009 | 414,946 | 121,052 | 21,832,968 | 529,670 | — | — | 22,898,636 |
| 2008 | 69,798 | 84,283 | 22,706,281 | 341,709 | — | — | 23,202,071 |
| 2007 | 210,099 | 76,982 | 22,425,213 | 335,401 | — | — | 23,047,695 |
| 2006 | 125,442 | 100,094 | 21,571,357 | 494,213 | — | — | 22,291,106 |
| 2005 | 127,342 | 129,604 | 22,467,576 | 619,138 | — | — | 23,343,660 |
| 2004 | 60,315 | 131,151 | 21,858,088 | 671,127 | — | — | 22,720,681 |
| 2003 | 159,143 | 96,067 | 21,966,624 | 786,813 | — | — | 23,008,647 |
| 2002 | 167,892 | 82,264 | 21,612,501 | 409,502 | — | — | 22,272,159 |
| 2001 | 199,296 | 62,625 | 19,212,043 | 178,605 | — | — | 19,652,569 |
Projects 10
Capacity
4.12 GW
0.07 GW active
3 no longer listedNo longer listedThese projects were last stated as active but are no longer listed in any register, so they are not counted as active.
| Status | Name. Sort by name, A to Z | Type | MW, sorted descending. Sort by capacity, smallest first | State | Online. Sort by proposed online date, latest first | Source |
|---|---|---|---|---|---|---|
| Postponed | NA 1 (NC) | Gas, combined cycle | 3,132.3 MW | NC | — | EIA-860M |
| Postponed | Future Gen Plant 2 | Gas, combined cycle | 612 MW | NC | — | EIA-860M |
| Postponed | Future Gen Plant 1 | Gas, combined cycle | 211.8 MW | NC | — | EIA-860M |
| Under construction | New Hill 1 Battery | Storage | 56 MW | NC | Online Sep 1, 2027 | LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions) |
| Postponed | Woodfin | Gas, combustion turbine | 45.5 MW | NC | — | EIA-860M |
| Under construction | Elm City BESS | Storage | 20 MW | NC | Online Sep 1, 2026 | EIA-860M |
| Under construction | Asheville BESS | Storage | 17.3 MW | NC | Online Sep 1, 2026 | EIA-860M |
| Under construction | Warsaw 2 Energy Storage | Storage | 11 MW | NC | Online Sep 1, 2026 | EIA-860M |
| Under construction | Asheville Solar | Solar | 9.5 MW | NC | Online Dec 1, 2026 | LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions) |
| Postponed | Riverside BESS | Storage | 5 MW | NC | — | EIA-860M |
Sources EIA-860M · Berkeley Lab
Assets 32
Assets
32
Capacity
16,077 MW
- Gas, combined cycle: 5,175 MW, 4 assets
- Coal: 5,023 MW, 5 assets
- Nuclear: 3,723 MW, 3 assets
- Gas, combustion turbine: 1,296 MW, 2 assets
- Oil: 274 MW, 3 assets
- Other: 586 MW, 15 assets
Operates 31 power plants · Owns 1 power plant
Sources
- EIA-860M
- GEMGlobal Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License.
Ownership 1
Companies
1
Parents
1
Subsidiaries
0
direct
-
Duke Energy Ultimate parent 144 assets62,152 MWwith the companies below
-
Duke Energy Progress - (NC) This company · share not stated 28 assets14,359 MW
-
Duke Energy Carolinas, LLC Subsidiary · share not stated 46 assets23,868.3 MW
-
Duke Energy Florida, LLC Subsidiary · share not stated 46 assets13,649.9 MW
-
Duke Energy Florida Solar Solutions Subsidiary · share not stated 1 asset4.9 MW
-
Duke Energy Indiana, LLC Subsidiary · share not stated 15 assets7,812.6 MW
-
Duke Energy Kentucky Inc Subsidiary · share not stated 6 assets1,352.5 MW
-
Duke Energy Ohio Inc Subsidiary · share not stated 3 assets1,876.8 MW
-
The same companies as a table, with each ownership claim
| Company. Sort by company, A to Z | Relationship, sorted ascending. Sort by relationship, subsidiaries first | Assets. Sort by assets held, largest first | Asset types |
|---|---|---|---|
| Duke EnergyOwnership link recorded from the companies' own published statements; no date stated by the source. | Parent | — | — |
Sources 4
Registers
4
Reuse terms
- 2 Open license
- 2 Open license, with credit
Latest read
2026-11-04
From its recordsSourcesThe registers behind this company's assets, projects and RFPs; the company record itself is derived from them.
Sources
-
View at source →
EIA-860M ·
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain
Summary only: the source’s license keeps the full record at the source.
-
View at source →
GEM ·
Global Energy Monitor — Global Integrated Power Tracker (unit-level power plants, eight technologies, all statuses)
Global Integrated Power Tracker, Global Energy Monitor, September 2026 release (https://globalenergymonitor.org/projects/global-integrated-power-tracker), CC BY 4.0. Modified by Inframation: TransitionZero-sourced rows removed; statuses and technologies mapped to Inframation's vocabulary; figures aggregated. Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License. · license
In-file notice, About sheet of Global_Integrated_Power_September_2026_V2.xlsb (the owner's download, read 2026-10-26 with pyxlsb 1.0.10; decisions log 2026-10-26): "Copyright © Global Energy Monitor. Global Integrated Power Tracker, September 2026 release. Distributed under a Creative Commons Attribution 4.0 International License. (See the CC license for attribution requirements if sharing or adapting the data set.)" and "Please note records with a “TZ ID” in the Other IDs (unit/phase) column were partially or fully sourced from the TransitionZero, Solar Asset Mapper, August 2025. Copyright © TransitionZero, Solar Asset Mapper, August 2025. Distributed under a Creative Commons Attribution-Non-Commercial 4.0 International License (CC BY-NC 4.0)." Before it was read: no licence prose on the dataset page (retrieved 2026-10-23), which gives only "The recommended citation is "Global Integrated Power Tracker, Global Energy Monitor, September 2026 release.""; GEM's download form records "Creative Commons Attribution 4.0 International (CC BY 4.0) — /creative-commons-license" (https://api.globalenergymonitor.org/static/gem-download-form.bundle.js, sha256 e5ecbeab…905e5b, retrieved 2026-10-23).
Summary only: the source’s license keeps the full record at the source.
-
View at source →
Berkeley Lab ·
LBNL "Queued Up" project-level interconnection queue data file (non-ISO regions)
Lawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker. · license
Publication page https://eta-publications.lbl.gov/publications/queued-2026-edition-characteristics, retrieved 2026-10-23 (HTTP 200) — "Copyright Notice: The Queued Up data file is licensed CC BY 4.0. You may use, share, or adapt the dataset as long as you attribute it to Lawrence Berkeley National Laboratory and GridTracker." and "Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker. CC BY 4.0. All rights reserved." The file's Introduction sheet adds the DOE contract notice ("This dataset has been authored by an author at Lawrence Berkeley National Laboratory under Contract No. DE-AC02-05CH11231 with the U.S. Department of Energy ...") and the standard no-warranty disclaimer
-
View at source →
EIA-860M ·
EIA-860M Preliminary Monthly Electric Generator Inventory
US federal work — public domain
Around this company
Nearby 66
within 15 miProjects
66
within 15 mi
Nearest
0.0 mi
Asheville BESS
All 66NearbyShowing all 66 nearby projects. The 50 nearest are listed.
| Status | Name. Sort by name, A to Z | Type | MW. Sort by capacity, largest first | Distance, sorted ascending. Sort by distance, farthest first | Nearest asset |
|---|---|---|---|---|---|
| Under construction | Asheville BESS | Storage | 17.3 MW | 0.0 mi away | nearest: Asheville BESS |
| Under construction | Elm City BESS | Storage | 20 MW | 0.0 mi away | nearest: Elm City BESS |
| Under construction | Warsaw 2 Energy Storage | Storage | 11 MW | 0.0 mi away | nearest: Warsaw 2 Energy Storage |
| Under construction | Asheville Solar | Solar | 9.5 MW | 0.1 mi away | nearest: Asheville BESS |
| Built | AMAZON DATA SERVICES, INC. - ENERGY WAY TECH CAMPUS | Large load | — | 0.7 mi away | nearest: Sherwood H Smith Jr Energy Complex |
| Postponed | Fairfield Solar | Solar | 10 MW | 1.1 mi away | nearest: Darlington County |
| Postponed | Fishwater Solar | Solar | 2 MW | 1.2 mi away | nearest: Darlington County |
| Postponed | Riverside BESS | Storage | 5 MW | 1.2 mi away | nearest: Woodfin Solar |
| Under construction | Craggy Energy Storage | Storage | 30.5 MW | 1.4 mi away | nearest: Woodfin Solar |
| Postponed | Lake Solar Center LLC | Solar | 5 MW | 1.4 mi away | nearest: Elm City BESS |
| Filed | Robinson Solar Plant | Solar | 76 MW | 1.5 mi away | nearest: Darlington County |
| Postponed | Angus Holdings | Solar | 5 MW | 1.6 mi away | nearest: Warsaw 2 Energy Storage |
| Postponed | Higgins Solar | Solar | 5 MW | 1.8 mi away | nearest: Red Bud Solar Plant |
| Filed | Stevens Mill Solar | Solar | 80 MW | 1.8 mi away | nearest: Wayne County Energy Complex |
| Postponed | Dadswell Solar | Solar | 1 MW | 1.9 mi away | nearest: H B Robinson |
| Under construction | New Hill 1 Battery | Storage | 56 MW | 1.9 mi away | nearest: Harris (NC) |
| Postponed | Bonnie Solar | Solar | 5 MW | 2.3 mi away | nearest: Red Bud Solar Plant |
| Postponed | Woodfin | Gas, combustion turbine | 45.5 MW | 2.4 mi away | nearest: Woodfin Solar |
| Postponed | Eisenhower Solar | Solar | 5 MW | 2.4 mi away | nearest: Red Bud Solar Plant |
| Announced | Robeson Solar I | Solar + storage | 108 MW | 3.0 mi away | nearest: W H Weatherspoon |
| Filed | Hyco Solar LLC | Solar | 80 MW | 3.3 mi away | nearest: Roxboro |
| Postponed | Guernsey Holdings | Solar | 5 MW | 3.7 mi away | nearest: Tillery |
| Postponed | Innovative Solar 68 | Solar | 48.3 MW | 3.8 mi away | nearest: DD Fayetteville Solar NC LLC |
| Postponed | Soy Solar | Solar | 5 MW | 4.0 mi away | nearest: W H Weatherspoon |
| Permitted | Lotus Solar | Solar | 75 MW | 4.1 mi away | nearest: Darlington County |
| Postponed | Bradley Farm (Dudley) | Solar | 5 MW | 4.9 mi away | nearest: Lee Combined Cycle Plant |
| Postponed | Roady Lane Farm LLC | Solar | 74.8 MW | 4.9 mi away | nearest: Lee Combined Cycle Plant |
| Announced | Powells Creek Solar - Hybrid | Storage | 17.5 MW | 5.5 mi away | nearest: Roxboro |
| Under construction | B & K Solar | Solar | 74.9 MW | 5.7 mi away | nearest: H B Robinson |
| Postponed | Howardtown Farm | Solar | 10 MW | 6.2 mi away | nearest: DD Fayetteville Solar NC LLC |
| Postponed | Middleton Solar | Solar | 2 MW | 6.4 mi away | nearest: H B Robinson |
| Postponed | Madison Solar | Solar | 10.9 MW | 6.5 mi away | nearest: H B Robinson |
| Permitted | GEB Solar | Solar | 50 MW | 6.7 mi away | nearest: H B Robinson |
| Postponed | MP Wilson LLC | Biomass | 2.2 MW | 6.7 mi away | nearest: Elm City Solar Facility |
| Postponed | Carter Solar | Solar | 5 MW | 7.5 mi away | nearest: Red Bud Solar Plant |
| Postponed | Sadie Solar | Solar | 5 MW | 7.6 mi away | nearest: Wayne County Energy Complex |
| Postponed | Chatham Park Solar Farm | Solar | 20 MW | 7.7 mi away | nearest: Cape Fear |
| Postponed | Hawk Solar | Solar | 5 MW | 7.8 mi away | nearest: Red Bud Solar Plant |
| Postponed | Faison Farm | Solar | 5 MW | 8.2 mi away | nearest: Warsaw Farm |
| Under construction | Gum Swamp Solar, LLC | Solar | 80 MW | 8.3 mi away | nearest: Sherwood H Smith Jr Energy Complex |
| Postponed | Signature Solar | Solar | 5 MW | 8.3 mi away | nearest: Wayne County Energy Complex |
| Postponed | Louisburg Solar | Solar | 5 MW | 8.5 mi away | nearest: Red Bud Solar Plant |
| Permitted | Rollins Solar | Solar | 74.9 MW | 8.8 mi away | nearest: H B Robinson |
| Postponed | Clayton Solar | Solar | 5 MW | 8.8 mi away | nearest: Red Bud Solar Plant |
| Postponed | Longleaf Solar | Solar | 5 MW | 8.9 mi away | nearest: Wayne County Energy Complex |
| Postponed | E Nash PV3 | Solar | 26 MW | 9.0 mi away | nearest: Red Bud Solar Plant |
| Postponed | FibroCoast | Biomass | 60 MW | 9.0 mi away | nearest: Warsaw Farm |
| Built | HOSTED SOLUTIONS ACQUISITION - NORTH RALEIGH ** INACTIVE ** | Large load | — | 9.4 mi away | nearest: Knightdale Battery |
| Postponed | Wilfork Solar | Solar | 5 MW | 9.4 mi away | nearest: HF Lee Plant |
| Postponed | Hilly Branch | Solar | 2 MW | 9.8 mi away | nearest: W H Weatherspoon |
Sources EIA-860M · Berkeley Lab · EPA ICIS-Air
Sources
- EIA-860M
- Berkeley LabLawrence Berkeley National Laboratory and GridTracker, Queued Up data file (2026 edition), CC BY 4.0. Modified by Inframation: non-ISO and MISO regions only; MISO rows labelled with the date the file's queue data runs to; statuses and technologies mapped to Inframation's vocabulary. Queued Up Data File. Copyright (c) 2026, The Regents of the University of California, through Lawrence Berkeley National Laboratory (subject to receipt of any required approvals from the U.S. Dept. of Energy) & GridTracker.
- EPA ICIS-Air